Four MBTA lines close for days at a time in December starting Dec. 4

Riders on four MBTA lines will lose service for days at a time in December, starting Friday, Dec. 4, when Green Line, Framingham/Worcester Line and Needham Line trains stop on long stretches into Boston.
Shuttles and buses will cover the gaps. Trips will run 30 to 40 minutes longer, the MBTA said in its announcement of the December construction work.
From Dec. 4 to 7, no Green Line trains will run between North Station and four points on the branches: Babcock Street on the B, St. Mary's on the C, Brookline Hills on the D and Heath Street on the E.
Crews will use the four days to lay signal cables and fiber optics, add junction boxes and rework switches, curbs and platform edges so the new, larger Type 10 cars can clear them.
Free accessible shuttle buses will connect riders with the Orange Line at Back Bay, and Route 39 buses will take the place of the E branch.
Accessible vans will run only at downtown Boston stations, and Green Line riders should allow 35 more minutes, the MBTA said.
Much of that work goes toward replacing the line's signal system, which the MBTA said is more than 100 years old. "These operational improvements mean more reliable service for riders with fewer unplanned disruptions and emergency repairs caused by the older, aging signal system," the agency said.
Through Thursday, Dec. 10, inbound trains will skip Hawes Street and Summit Avenue. E branch trains pass by Symphony Station, which stays closed until spring 2029 for accessibility upgrades that include four new elevators.
West of Boston, Commuter Rail trains on the Framingham/Worcester Line won't run between Framingham and South Station for three days, Dec. 4 to 6.
Four free shuttle bus routes will take their place, and the MBTA told riders to budget at least 30 extra minutes.
In Needham, trains will stop between Needham Heights and South Station at about 11 p.m. on Friday, Dec. 4, and stay off through the weekend of Dec. 5 and 6. MassDOT is using the break to replace the West Roxbury Parkway bridge over the tracks.
No shuttle will run on the Needham Line. Instead, riders can take bus routes 35, 36, 37 and 59, and they should allow at least 35 more minutes.
Blue Line riders get the longest shutdown, nine days without trains between Bowdoin and Orient Heights from Saturday, Dec. 12, through Sunday, Dec. 20. Crews will rebuild the track from the ground up, put in new ties and rail and resurface the rail.
Free accessible shuttles will run from Orient Heights to Haymarket, where riders can change to the Orange and Green lines. Those riders should add 40 minutes, the MBTA said.
Closing a line for several days is the most efficient way to get the work done, the agency said. "This work cannot be performed during the overnight hours when the MBTA does not operate, and would be extremely inefficient and costly if planned during single weekend outages," the MBTA said.
Station signs and announcements will spell out the changes, and so will MBTA.com/PlannedWork.
Before the Blue Line closes, the MBTA will hold a virtual public meeting on Monday, Nov. 30, about the work and how riders can get around during the shutdown.