MBTA riders face 100 planned outage days in 2027, down from 274 in 2024

A green MBTA Green Line train arrives at Longwood station as passengers wait on the platform on a gray winter day.
Photo: IliketrainsR211T / Wikimedia Commons (CC BY 4.0)

Planned shutdowns will cost MBTA riders far fewer days next year, with the transit agency expecting 100 days of service outages in 2027, compared with 274 in 2024.

That's 174 fewer outage days than in 2024, and 32 fewer than in 2026.

On the subway, most of the interruptions will come on weekends, the MBTA said in its 2027 construction schedule.

Next year's work centers on new signals for the Red and Orange lines, new signals in the Green Line's central tunnel ahead of new Type 10 vehicles, track maintenance and radio upgrades.

Green Line riders feel it first. Signal work shuts down service through the central tunnel on Jan. 9-10, Jan. 16-24, Feb. 6-7, Feb. 20-21 and Feb. 27-28.

In Newton, crews repairing the Hammond Street Bridge over the D Branch will halt trains between Reservoir and Riverside on Aug. 21-22 and Aug. 27-30.

Along Commonwealth Avenue, crews will raise B Branch platforms eight inches for boarding. Trains won't run between Babcock Street and Boston College on the weekends of Dec. 4-5, 11-12 and 18-19.

From April 8 to 12, Red Line trains won't run between JFK/UMass and Quincy Center while crews work on signals. A longer closure comes Aug. 7-15, when track work and work at the Furnace Brook Parkway Bridge shut the line between JFK/UMass and Braintree.

Orange Line riders lose service between North Station and Ruggles on May 15-23 for track work. Then on Oct. 8-11, trains stop between North Station and Back Bay so crews can put in two transfer elevators at Downtown Crossing.

Track work closes the Blue Line between Bowdoin and Airport on June 18-27.

Mattapan Line trains won't run between Ashmont and Mattapan on March 27-28 and April 3-4.

Symphony Station stays closed through spring 2029 while crews build four new elevators and make other accessibility upgrades.

Commuter rail riders get their own disruptions. On the Needham Line, service between Forest Hills and Needham Heights faces weekly off-peak weekday disruptions, from 9 a.m. to 3:30 p.m., between March 1 and May 21 while crews work on track ties.

Track upgrades at Newtonville will stop Worcester Line trains between Back Bay and Framingham on June 5-6 and June 26-27.

On the Newburyport/Rockport Line, weekday service between Newburyport and Ipswich will see disruptions every week from March 8 to June 30.

Phillip Eng, the MBTA's general manager and CEO and the interim secretary of transportation, said 65 percent of the system wasn't in a state of good repair in 2023. Work since 2024 has made progress, he said.

Those repairs have "provided riders with faster, more reliable trips, and given them back precious minutes in their day," Eng said.

"I want to personally thank the public for their patience," he said.

Crews will bundle projects so each shutdown gets as much work done as possible, the MBTA said.

Dates could still change. Before each interruption, riders will get notice of the shuttle buses and alternate routes, the agency said.